Skilled Nursing Facilities

Contents

Closing or Striking out a Quality Improvement Project (QIP)

You can close a completed QIP or Strike out a QIP that was created in error.

Warning

After a QIP is Closed or Struck out, it cannot be edited or reactivated.

  1. Analytics > QIP > select QIP > Outcomes.

  2. Click Close or Strike Out.

    • Close QIP - Use if a QIP is completed.

      • Achieved Desired Results, Achieved Partial Results, or No Improvement. 

      • The best match is selected, based on Current Goal Values. You can edit selection.

      • Select Adopt, Adapt, or Abandon. 

      • Follow-up Plan: Describe the follow up plan or explain the reason for Adapting or Abandoning the PIP. (1000 Characters) *This area is required if ‘No Improvement’ is selected.

    • Strike out a QIP - Use if a QIP is created in error. Click to open a note box to explain the reason for Striking out the QIP (1000 Characters)

  • You must have appropriate security permissions to Close or Strike out a QIP.